NASA's First Space Station - Skylab
(from
http://april.friends-partners.ru/partners/mwade/craft/skylab.htm )
Craft Crew Size: 3 - on station
Design Life: 600 days.
Orbital Storage: 730.00 days.
Total Length: 36.1 m.
Maximum Diameter: 6.6 m.
Total Habitable Volume: 361.00 m³.
Total Mass: 76,295 kg (76.3 MT).
Electric system: 11.00 total average kW.
Electrical System: Solar Panels, 2 Wings + 4 Windmill, each 14.94 m l.
Project began life as Apollo Orbital Workshop - outfitting of an S-IVB stage with docking adapter with equipment launched by several subsequent S-1B launches. Curtailment of the Apollo moon landings meant that surplus Saturn V's were available, so the pre-equipped, five times heavier, and much more capable Skylab resulted.
External solar/meteoroid shield ripped off during ascent, tearing away one solar panel wing and debris jamming the remaining panel. Without shield temperatures soared to 52°C (126°F). Launch of the crew was delayed for 10 days to develop procedures and crew training to make the workshop habitable. Repairs by subsequent crews led to virtually all mission objectives being met. Skylab re-entered on July 11, 1979.
Payload: Imaging cameras. White-light coronagraph. Ultraviolet scanning polychromator- spectroheliometer. Extreme ultraviolet and X-ray telescope. Space manufacturing experiments. Externally mounted Earth resources instruments included a multispectral imaging camera, an Earth terrain camera, an infrared spectrometer, a multispectral scanner, a microwave radiometer/scatterometer and altimeter, and an L-band microwave radiometer.
Module: Airlock Module. Purpose: Airlock for EVA's, mounting of STS and TNL. Length: 5.4 m. Basic Diameter: 1.7 m. Max Diameter: 3.0 m. Overall Mass: 22,225 kg.
Module: Apollo Telescope Mount. Purpose: Solar Telescope module. Length: 3.4 m. Basic Diameter: 2.1 m. Max Diameter: 2.1 m. Overall Mass: 11,180 kg. Electric system: 11.00 average kW. Electric system type: Solar Panels, Windmill, four, each 14.94 m long.
Module: Instrument Unit. Purpose: Used for guidance during orbital insertion only. Length: 0.9 m. Basic Diameter: 6.6 m. Max Diameter: 6.6 m. Overall Mass: 2,065 kg.
Module: Multiple Docking Adapter. Purpose: Docking module for two CSM, one ATM. Length: 5.3 m. Basic Diameter: 3.0 m. Max Diameter: 3.0 m. Overall Mass: 6,260 kg.
Module: Orbiting Work Shop. Purpose: Main laboratory. Length: 14.7 m. Basic Diameter: 6.6 m. Max Diameter: 6.6 m. Overall Mass: 35,380 kg. RCS Coarse No x Thrust: Reaction wheels. Electric system type: Solar Panels, (in operation only one deployed).
Module: Station core. Purpose: Space station civilian. Modules.Crew Size: 3. Length: 36.1 m. Basic Diameter: 6.6 m. Max Diameter: 6.6 m. Habitable Volume: 361.00 m3. Overall Mass: 76,295 kg. RCS Coarse No x Thrust: Reaction wheels. Electric system.
======================================================
Information is from the Mark Wade's website, Encyclopedia Astronautica,
http://www.astronautix.com/spaceflt.htmFormatted by Steve Scherer, mailto:stevescherer@yahoo.com
Skylab 1
14 May 1973
Spacecraft: Skylab.
Mass: 74,783 kg.
Launch Site: Cape Canaveral.
Launch Vehicle: Saturn V.
First US space station. Project began life as Apollo Orbital Workshop - outfitting of an S-IVB stage with docking adapter with equipment launched by several subsequent S-1B launches. Curtailment of the Apollo moon landings meant that surplus Saturn V's were available, so the pre-equipped, five times heavier, and much more capable Skylab resulted.
External solar/meteoroid shield ripped off 63 seconds into ascent, tearing away one solar panel wing and debris jamming the remaining panel. Without shield temperatures soared in station. Repairs by crews led to virtually all mission objectives being met.
Following the final manned phase of the Skylab mission, ground controllers performed some engineering tests of certain Skylab systems--tests that ground personnel were reluctant to do while men were aboard. Results from these tests helped to determine causes of failures during the mission and to obtain data on long term degradation of space systems.
Upon completion of the engineering tests, Skylab was positioned into a stable attitude and systems were shut down. It was expected that Skylab would remain in orbit eight to ten years. It was to have been visited by an early shuttle mission, reboosted into a higher orbit, and used by space shuttle crews. But delays in the first flight of the shuttle made this impossible.
Skylab 2
Crew: Conrad, Kerwin, Weitz
25 May 1973 13:00 GMT.
Duration: 28.03 days.
Call Sign: Skylab.
Backup Crew: McCandless, Musgrave, Schweickart.
Launch Site: Cape Canaveral. Launch Complex: LC39B.
Launch Vehicle: Saturn IB.
LV Configuration: Saturn IB s/n SA-206.
Payload: Apollo CSM 116. Mass: 19,979 kg.
Location of Spacecraft: Naval Aviation Museum, Pensacola, FL.
Perigee: 425 km. Apogee: 440 km. Inclination: 50.0 deg. Period: 93.2 min.
Epic repair mission which brought Skylab into working order. Included such great moments as Conrad being flung through space by the whiplash after heaving on the solar wing just as the debris constraining it gave way; deployment of a lightweight solar shield, developed in Houston in one week, which brought the temperatures down to tolerable levels. With this flight US again took manned spaceflight duration record.
The Skylab space station was launched May 14, 1973, from the NASA Kennedy Space Center by a huge Saturn V launch vehicle, the moon rocket of the Apollo Space Program. Sixty-three seconds after liftoff, the meteoroid shield--designed also to shade Skylab's workshop--deployed inadvertently. It was torn from the space station by atmospheric drag. This event and its effects started a ten-day period in which Skylab was beset with problems that had to be conquered before the space station would be safe and habitable for the three manned periods of its planned eight-month mission.
When the meteoroid shield ripped loose, it disturbed the mounting of workshop solar array "wing" two and caused it to partially deploy. The exhaust plume of the second stage retro-rockets impacted the partially deployed solar array and literally blew it into space. Also, a strap of debris from the meteoroid shield overlapped solar array "wing" number one such that when the programmed deployment signal occurred, wing number one was held in a slightly opened position where it was able to generate virtually no power.
In the meantime, the space station had achieved a near-circular orbit at the desired altitude of 435 kilometers (270 miles). All other major functions including payload shroud jettison, deployment of the Apollo Telescope Mount (Skylab's solar observatory) and its solar arrays, and pressurization of the space station occurred as planned.
Scientists, engineers, astronauts, and management personnel at the NASA Marshall Space Flight Center and elsewhere worked throughout the first ten-day period of Skylab's flight to devise the means for its rescue. Simultaneously, Skylab--seriously overheating--was maneuvered through varying nose-up attitudes that would best maintain an acceptable "holding" condition. Because of the loss of the meteoroid shield, however, this positioning caused workshop temperatures to rise to 52° Celsius (126° F). During that ten-day period and for some time thereafter, the space station operated on less than half of its designed electrical system, in the partially nose-up attitudes, was generating power at reduced efficiency. The optimum condition that maintained the most favorable balance between Skylab temperatures and its power generation capability occurred at approximately 50 degrees nose-up.
The crew rendezvoused with Skylab on the fifth orbit. After making substantial repairs, including deployment of a parasol sunshade which cooled the inside temperatures to 23.8° C (75° F), by June 4 the workshop was in full operation. In orbit the crew conducted solar astronomy and Earth resources experiments, medical studies, and five student experiments; 404 orbits and 392 experiment hours were completed; three EVAs totalled six hours, 20 minutes.
Skylab-2 Manhour Utilization
Medical Activities - 145.3 hours, 7.5%
Solar Observations - 117.2 hours, 6%
Earth Resources - 71.4 hours, 3.7%
Other Experiments - 65.4 hours, 3.4%
Sleep, Rest & Off Duty - 675.6 hours, 34.7%
Pre/Post Sleep & Eating - 477.1 Hours, 24.5%
Housekeeping - 103.6 hours, 5.3%
Physical Training & Personal Hygiene - 56.2 hours, 2.9%
Other(EVA)Etc. - 232.5 hours, 12%
Total: 1944.3 hours
Skylab 3
Crew: Bean, Garriot, Lousma
28 July 1973 11:10 GMT.
Duration: 59.46 days.
Call Sign: Skylab.
Backup Crew: Brand, Lenoir, Lind.
Launch Site: Cape Canaveral. Launch Complex: LC39B.
Launch Vehicle: Saturn IB.
LV Configuration: Saturn IB s/n SA-207.
Payload: Apollo CSM 117. Mass: 20,121 kg.
Location of Spacecraft: NASA Lewis Research Center, Cleveland, OH.
Perigee: 422 km. Apogee: 442 km. Inclination: 50.0 deg. Period: 93.2 min.
Continued maintenance of the Skylab space station and extensive scientific and medical experiments. Installed twinpole solar shield on EVA; performed major inflight maintenance; doubled record for length of time in space. Completed 858 Earth orbits and 1,081 hours of solar and Earth experiments; three EVAs totalled 13 hours, 43 minutes.
Skylab-3 Manhour Utilization
Medical Activities - 312 hours, 8%
Solar Observations - 305.1 hours, 7.8%
Earth Resources - 223.5 hours, 5.7%
Other Experiments - 243.6 hours, 6.2%
Sleep, Rest & Off Duty - 1224.5 hours, 31.2%
Pre/Post Sleep & Eating - 975.7 hours, 24.8%
Housekeeping - 158.4 hours, 4%
Physical Training & Personal Hygiene - 202.2 hours, 5.2%
Other (EVA) Etc. - 279.7 hours, 7.1%
Total 3925.2 hours
Skylab 4
Crew: Carr, Gibson Edward, Pogue
16 November 1973 14:01 GMT.
Duration: 84.05 days.
Call Sign: Skylab.
Backup Crew: Brand, Lenoir, Lind.
Launch Site: Cape Canaveral. Launch Complex: LC39B.
Launch Vehicle: Saturn IB.
LV Configuration: Saturn IB s/n SA-208.
Payload: Apollo CSM 118. Mass: 20,847 kg.
Location of Spacecraft: National Air and Space Museum (Smithsonian Institution), Washington, DC.
Perigee: 422 km. Apogee: 437 km. Inclination: 50.0 deg. Period: 93.1 min.
Included observation and photography of Comet Kohoutek among numerous experiments. Completed 1,214 Earth orbits and four EVAs totalling 22 hours, 13 minutes. Increased manned space flight time record by 50%. Rebellion by crew against NASA Ground Control overtasking led to none of the crew ever flying again.
Skylab-4 Manhour Utilization
Medical Activities - 366.7 hours, 6.1%
Solar Observations - 519 hours, 8.5%
Earth Resources - 274.5 hours, 4.5%
Other Experiments - 403 hours, 6.7%
Sleep, Rest & Off Duty - 1846.5 hours, 30.5%
Pre/Post Sleep & Eating - 1384 hours, 23%
Housekeeping - 298.9 hours, 4.9%
Physical Training & Personal Hygiene - 384.5 hours, 6.4%
Other (EVA) Etc. - 571.4 hours, 9.4%
Total: 6048.5 hours
Skylab Statistical Summary
Orbital Parameters, 268.1 x 269.5 miles
Orbital Inclination, 50 degrees
Orbital Period, approx. 93 minutes
Distance Traveled in miles (manned):
Skylab 2 - 11.5 million
Skylab 3 - 24.5 million
Skylab 4 - 34.5 million
total - 70.5 million miles
Mission Duration:
Skylab 2 - 28 days, 49 minutes
Skylab 3 - 59 days, 11 hrs., 9 min.
Skylab 4 - 84 days, 1 hr., 16 min.
total - 171 days, 13 hrs., 14 min.
On July 11, 1979, Skylab disintegrated when it re-entered the earth's atmosphere after a worldwide scare over its pending crash. The debris stretched from the south-east Indian Ocean into Western Australia.
--------------------------------------------------------
http://www.astronautix.com/craft/apoloatm.htmChronology of Skylab